Agenda item

Minutes:

            The Committee considered the undernoted report:

 

“Relevant Background Information

 

      Construction began at Grove Wellbeing Centre on 29th August 2005 and in line with a projected 24 month build programme, the original completion date was identified as 29th August 2007.

 

At the Community and Leisure Services Sub Committee of 3rd April 2007, Members were advised that the target completion date for construction of the project was 12th November 2007 however, due to the necessity to incorporate landscape works within the project to the value of £1,064,400 associated with funding received from Belfast Regeneration Office, the construction completion date had to be adjusted and the earliest completion date was projected as 4th February 2008.

 

      The building was actually handed over from the contractor to the Council on Friday 21st March and Members were advised at the Parks and Leisure meeting on 11th October 2007 that a period of approximately 2 months would be required to enable the commissioning of plant, service testing, staff training and familiarisation, before the new facility becomes available for public use and fully operational.

 

      At the Parks and Leisure Committee on 14th February 2008 Members agreed to refer to the Council at its meeting on 3rd March the question of the closure of the Grove Leisure Centre.  The Committee also agreed that, in the event of the closure of the Centre, there should be a seamless transfer of operations from the Grove Leisure Centre to other Council facilities and agreed to the allocation of the necessary resources and to the restriction of the use of the Grove Leisure Centre during that period to clubs only.

 

      At the monthly meeting of Belfast City Council on Monday 3rd March 2008, the decision was taken to close the Grove Leisure Centre and examine uses for the site which would maximise benefits to the area.

 

      At the monthly meeting of Belfast City Council on Tuesday 1st April, the decision was taken to keep the fitness suite at Grove open to the public.  Officers will update Committee on 10th April on the arrangements that have been made.

 

Key Issues

 

      Key issues during the next 2 months;

 

1)   In order to achieve the objective of a seamless transfer for clubs it is necessary to provide adequate staffing levels at the existing site until the new facility opens.  Designations affected by this decision include, receptionists, leisure attendants, swim teachers, cleaners and staff involved in duty management and all affected designations have the opportunity to work at both sites. Staff will remain onsite in the Grove Leisure Centre on a rotating basis and will ensure the safety of the clubs and groups as well as assisting with the closing down of the old centre.

 

2)   This 2 month pre-opening is necessary to complete all the work on the snagging list and for the delivery and installation of equipment and also to facilitate training, both BCC site specific training and joint training with the BHSCT & BELB as well as operations testing prior to opening. 

 

3)   The process to recruit the additional staff for the centre, as approved by Members at the Parks & Leisure Committee on 13th March 2008 is currently underway and it is anticipated that these posts will be filled prior to the centre opening.

 

4)   Ten pin bowling alley – two tenders have been received for installation of bowling equipment and advice is currently being sought from the Procurement Section as a result of the poor standard of response. It is anticipated that the bowling alley will now not open at the same time as all of the other leisure facilities.

 

5)   Following the decision by Members at the Parks and Leisure Committee on 13th March 2008 regarding franchise catering for Leisure Centres, the new quotation documents for the Grove Well Being Centre will be issued by Friday 4th April 2008.  It is still hoped that the successful caterer will be in place either before the centre opens in May or shortly afterwards.

 

6)   To assist with the smooth opening of the centre, and due to the technologically advanced nature of much of the plant, it is the intention to hold ‘field trials’. Invited groups will be asked to use facilities so that staff can test the systems in a realistic situation. The invitations will also be useful in promoting the Centre amongst potential users prior to opening.

 

      A full programme of tests, covering a six-day period, from Monday 19th - Saturday 24th May, and requiring groups representing a wide range of ability-levels, age?groups and special interests, is being produced at present by officers, and it is proposed that, since these tests are necessary for the effective operation of the centre, no charges be levied. It is further proposed that the first group to be given the opportunity to use the Centre during this period be the Elected Members and the suggested date is Monday 19th May.

 

7)   The delay in the handover of the building to the Council has impacted upon the proposed timing of an official opening ceremony to mark the occasion.  It is proposed that the centre will have ‘soft opening’ before the end of May and options will be presented to Members for consideration. Officers would welcome any suggestions regarding the ‘soft opening’ or for the official opening which is now proposed to take place in late September or early October 2008

 

Resource Implications

 

      Financial

 

      The cost of the official opening will depend on the decisions made, particularly in terms of the Official opening. All costs would be met from approved budgets.

 

      Human Resources

 

      There are no additional resources required to implement the recommendations of this report.

 

Recommendations

 

      Members are asked to note the contents of this report and to:

 

a.   Consider the nature and format of the ‘soft opening’.

b.   Approve the pre-opening field trials as outlined in the report.”

 

            The Director informed the Committee that an official opening ceremony would be held in late September or early October.  The opening of the leisure element of the centre to the public would also provide an opportunity to permit the media to tour the centre and to interview representatives of the Council, the Belfast Health and Social Care Trust and the Belfast Education and Library Board.  He also informed the Committee that the Council’s Reference Group on Older People was organising at the Centre on 29th May an Older People’s Convention.

 

            After discussion, it was

 

Moved by Councillor McCann,

Seconded by Councillor C. Maskey,

 

      That Councillor D. Browne be nominated to represent the Council at the “soft opening” ceremony for the Grove Wellbeing Centre.

 

Amendment

 

Moved by Councillor Stalford,

Seconded by Councillor Ekin,

 

      That the Right Honourable the Lord Mayor and the Chairman or Deputy Chairman of the Parks and Leisure Committee represent the Council at all opening ceremonies in connection with the Grove Wellbeing Centre.

 

            On a vote by show of hands five Members voted for the amendment and seven against and it was accordingly declared lost.

 

            The original proposal standing in the name of Councillor McCann and seconded by Councillor C. Maskey was thereupon put to the meeting when eight Members voted for and five against and it was accordingly declared carried.

 

            In addition, the Committee approved the arrangements in connection with the “pre-opening field trials” at the Grove Wellbeing Centre.

 

Supporting documents: